EnCana Corporation - S99A-014

AEC(W) plans to drill a minimumof 2 holes in this area. Depending on results and weather,the program could be extended to 4 holes.The wells are to be drilled for oil. Road construction and ice crossings are scheduled for midt o late December,drilling is dependent on condition of the ice road from Wrigley to Norman Wells. It is scheduled to start February 1, 2000, but would be started earlier if road conditions permit. Includes O-47 (wellsite and sump), P-16 (wellsite and sump), O-74 (wellsite and sump), D-7 (wellsite and campsite).