Subject to the terms and conditions of this Licence, the Licensee may divert water from Upper Panda Lake to Kodiak Lake, and use water and dispose of Waste for the purpose of mining the Panda, Koala, Koala North, Misery, Fox, and Jay kimberlite pipes, for operating the processing facilities and related infrastructure, and carrying out Reclamation associated with diamond mining within the Koala, Misery, King-Cujo, Desperation-Carrie, and Lac du Sauvage Watersheds of the Lac de Gras basin, Northwest Territories.This Licence entitles the Licensee to use water, Dewater Sable, Pigeon, and Beartooth Lakes for the purpose of mining, to Drawdown Two Rock Lake, divert Pigeon Stream around the Pigeon pit, pipe water from Bearclaw Lake outflow around Beartooth pit, and deposit Processed Kimberlite into a Processed Kimberlite Containment Area for the purpose of creating a pit lake. The Licensee may also dispose of Waste for industrial undertakings in diamond mining and processing, production, Reclamation and associated uses in the Koala, Pigeon, and Sable watersheds, Northwest Territories as shown on Figure 6, 8, & 10 of the Class A Water Licence and Land Use Permits supporting documents, submitted August 21, 2001.This Licence entitles the Licensee to Dewater Lynx Lake, use water, dispose of Waste, and divert runoff around the Lynx pit, for the purposes of mining the Lynx kimberlite pipe and carrying out Reclamation of the Lynx Development.This Licence also entitles the Licensee to Dewater a portion of Lac du Sauvage, use water, dispose of Waste, and divert streams B0 and Ac35 around the perimeter of the Dewatered area, for the purposes of mining the Jay kimberlite pipe and carrying out Reclamation of the Jay Development, as shown in Map 3.1-3 of the Updated Project Description submitted June 7, 2016.This Licence also entitles the Licensee to use water, dispose of Waste, and divert Groundwater inflows for the purposes of underground mining of the Misery kimberlite pipe and carrying out Reclamation of the Misery Underground Development, as described in the Application submitted August 15, 2017 and the additional information submitted during the regulatory process.The activities listed above are to be conducted as described in the Environmental Impact Assessments.


Documents

Uploaded On or After
Uploaded On or Before
Displaying 1 - 48 of 48
8. Closure and Reclamation
Interim Closure and Reclamation Plan
Document Received/Sent Uploaded
W2012L2-0001 - Ekati - ICRP Version 3.1 - Extension Request - Jul 6_21.pdf (150.29 KB)
W2012L2-0001 - Ekati - ICRP - Proposed Closure Objectives - Reasons for Decision - Jul 23_21.pdf (313.68 KB)
W2012L2-0001 - Ekati - ICRP - Proposed Closure Objectives - Review Summary and Attachments - Jul 14_21.pdf (1.02 MB)
W2012L2-0001 - Ekati - ICRP Version 3.1 - Proposed Objectives - Extension Request - Apr 14_21.pdf (3.05 MB)
W2012L2-0001 - Ekati - ICRP Version 3.1 - Proposed Revised Objectives - Apr 13_21.pdf (358.1 KB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Preworkshop Requirement 1 - Mar 17_21.pdf (818.19 KB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Preworkshop Requirement 2 - Mar 12_21.pdf (221.64 KB)
W2012L2-0001 - Ekati - ICRP Version 3.1 - Workshop Agenda - Mar 3_21.pdf (299.76 KB)
W2012L2-0001 - Ekati - Request to Defer CRP 3.1 Workshop - Reasons for Decision - Jan 14_21.pdf (177.05 KB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Extension Request to Workshop Date - Dec 23_20.pdf (243.9 KB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Extension Request to Workshop Date - May 6_20.pdf (400.07 KB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Approval of Workshop Extension Request - May 6_20.pdf (119.16 KB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Decision Letter and Reasons for Decision - Feb 19_20.pdf (1.32 MB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Review Summary and Attachments - Oct 17_19.pdf (3.08 MB)
W2012L2-0001 - Ekati - Effective NP - IEMA Recommendation and WLWB Response - Jun 13_19.pdf (352 KB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - ORS Extension Request - Board Decision - Mar 29_19.pdf (140.05 KB)
W2012L2-0001 - Ekati - ICRP - Version 3.0 - ORS Extension Request - Mar 12_19.pdf (79.77 KB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Technical Workshop - Follow-up Information - Feb 14_19.pdf (3.68 MB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Technical Workshop - Presentations - Jan 22_19.pdf (10.34 MB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Technical Workshop - Dominion Presentations - Jan 22_18.zip (17.6 MB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Technical Workshop - Agenda - Jan 22_19.pdf (159.55 KB)
W2012L2-0001 - Ekati - ICRP - Version 3.0 - RECLAIM Estimate - Aug 15_18.zip (376.58 KB)
W2012L2-0001 - Ekati - ICRP - Version 3.0 - Technical Memo on Effective NP - Aug 14_18.pdf (1.26 MB)
W2012L2-0001 - Ekati - ICRP - Version 3.0 - Lake Sediment Literature Review - Aug 14_18.pdf (710.32 KB)
W2012L2-0001 - Ekati - ICRP - Version 3.0 - Part 1 - Aug 15_18.pdf (22.67 MB)
W2012L2-0001 - Ekati - ICRP - Version 3.0 - Part 2 - Aug 15_18.pdf (21.55 MB)
W2012L2-0001 - Ekati - ICRP Version 3.0 - Extension Request - Board Decision - Jun 25_18.pdf (134.71 KB)
W2012L2-0001 - Ekati - ICRP - Version 3.0 - Extension Request - Jun 8_18.pdf (24.65 KB)
W2012L2-0001 - Ekati - ICRP - Extension Request - Correspondence - Jun 12_18.pdf (298.52 KB)
W2012L2-0001 - Ekati - ICRP - Dominion Workshop Materials Day 1 - February 27 2018 - Feb 26_18.pdf (5 MB)
W2012L2-0001 - Ekati - ICRP - Dominion Workshop Materials Day 2 - February 28 2018 - Feb 26_18.pdf (8.88 MB)
W2012L2-0001 - Ekati - ICRP - Dominion Workshop Agenda - February 27-28 2018 - Feb 26_18.pdf (129.72 KB)
W2012L2-0001 - Ekati - ICRP - 2013-2014 LLCF Reclamation Research Report - May 29_15.pdf (13.93 MB)
W2012L2-0001 - Ekati - ICRP - RP 4.2 Task 7 -2013 LLCF Site Investigation - Report - Jul 4_14.pdf (4.82 MB)
W2012L2-0001 - Ekati - ICRP - RP 4.2 Task 7 - 2013 LLCF Site Investigation - Appendix A to E - Jul 4_14.pdf (9.14 MB)
W2012L2-0001 - Ekati - ICRP - RP 4.2 Task 7 - 2013 LLCF Site Investigation - Appendix F to H - Jul 4_14.pdf (9.76 MB)
W2012L2-0001 - Ekati - ICRP - RP 4.2 Task 7 - 2013 LLCF Site Investigation - Appendix I to L - Jul 4_14.pdf (1.87 MB)
W2012L2-0001 - Ekati - ICRP - RP 7.1 Task 2 Past and Current TK Projects - Dec 18_13.pdf (705.7 KB)
W2012L2-0001 - Ekati - ICRP - RP 1.1 Task 1 Review Wildlife Barriers - Dec 18_13.pdf (1.9 MB)
W2012L2-0001 - Ekati - ICRP - RP 1.6 Task 1 Review In Pit Tailings Disposal - Dec 18_13.pdf (625.57 KB)
W2012L2-0001 - Ekati - ICRP - RP 7.1 Task 1 TK Literature Review - Dec 18_13.pdf (472.44 KB)
W2012L2-0001 - Ekati - ICRP - RP 7.2 Tasks 1 and 2 Literature Review - Dec 18_13.pdf (826.73 KB)
W2012L2-0001 - Ekati - 2013 Revegetion Projects Annual Report - May 8_14.pdf (4 MB)
W2012L2-0001 - Ekati - ICRP - LLCF Reclamation Pilot Study - RP 4.6 Task 2 - Dec 18_13.pdf (3.32 MB)
W2012L2-0001 - Ekati - ICRP - Old Camp Closure and Reclamation Plan - Dec 30_13.pdf (9.57 MB)
W2012L2-0001 - Ekati - ICRP - Old Camp Closure Plan - Board Directive - Sep 12_13.pdf (256.09 KB)
W2012L2-0001 - Ekati - ICRP - RP 1.3 Task 3 Pit Lake and Channel Elevations - Aug 15_13.pdf (11.76 MB)
W2012L2-0001 - Ekati - 2012 Revegetation Projects Annual Report - Aug 12_13.pdf (5.37 MB)