Dominion Diamond Mines ULC - W2016F0007

Construction of the Jay Road, including the cut through the esker; construction of the Jay Road North and the Jay Pipeline Road; Construction of a Pipeline bench; construction of caribou crossings; construction of laydown areas; construction and use of an esker cut stockpile location; use of explosives; establishment of infrastructure to support construction; and installation of a communications tower.
Uploaded On or After
Uploaded On or Before
Displaying 1 - 8 of 8
5. Reports and Studies
Designs and As-Builts
Document Received/Sent Uploaded
Ekati - Jay Early Works - DFO Response to Ac35 Water Crossing As-Built - Dec 20_18.pdf (114.13 KB)
Inspection Reports
Document Received/Sent Uploaded
Ekati - Jay Early Works - Land Use Inspection Report - October 19 2017 - Oct 27_17.pdf (1.11 MB)
Ekati - Jay Early Works - Land Use Inspection Report - September 6 2017 - Sep 13_17.pdf (1.04 MB)
Ekati - Jay Early Works - Land Use Inspection Report - August 9 2017 - Aug 28_17.pdf (1.6 MB)
Operations and Notifications
Document Received/Sent Uploaded
Ekati - Jay Early Works - Dominion Letter Re Temporary Suspension - Update 1 - Mar 27_20.pdf (1.37 MB)
Ekati - Jay Early Works - 48hr Notification of Construction - Jun 14 _17.pdf (207.69 KB)
Other
Document Received/Sent Uploaded
Ekati - Jay Early Works - DFO Letter Re Ac35 Fish Ladder - Dec 20_18.pdf (166.21 KB)
Ekati - Jay Early Works - Traditional Knowledge Management Framework - May 16_17.pdf (503.08 KB)