This Permit entitles Arctic Canadian Diamond Company Ltd. to conduct the following land-use operation:a) extraction and storage of waste rock and ore from the Misery Development;b) installation, operation, and maintenance of power lines and associated infrastructure as described in the application submitted August 15, 2017;c) operation, and maintenance of the Misery haul road and associated infrastructure;d) construction, use, and maintenance of supporting infrastructure at the Misery Development;e) use and expansion of the Misery camp;f) construction and maintenance of site facilities;g) construction and maintenance of a temporary ore stockpile;h) use of machinery and equipment to support construction and operations of the Misery pit;i) storage of fuel; andj) use of explosives
The Project is for Mining and Associated Activities in the Lac du Sauvage area, NT.

Documents

Uploaded On or After
Uploaded On or Before
Displaying 1 - 16 of 16
5. Reports and Studies
Inspection Reports
Document Received/Sent Uploaded
Misery Underground - Land Use Inspection Report - December 13 2023 - Dec 19_23.pdf (6.7 MB)
Misery Underground - Land Use Inspection Report - February 1 2024 - Feb 23_24.pdf (2.89 MB)
Misery Underground - Land Use Inspection Report - February 28 and March 14 2023 - May 05_23.pdf (4.08 MB)
Misery Underground - Land Use Inspection Report - December 7 2021 - Dec 17_21.pdf (3.14 MB)
Misery Underground - Land Use Inspection Report - January 28 2021 - Feb 15_21.pdf (10.99 MB)
Misery Underground - Land Use Inspection Report - November 27 2020 - Dec 11_20.pdf (4.98 MB)
Misery Underground - Land Use Inspection Report - October 22 2020 - Nov 4_20.pdf (8.8 MB)
Misery Underground - Land Use Inspection Report - February 6 2020 - Feb 21_20.pdf (4.72 MB)
Misery Underground - Land Use Inspection Report - December 10 2019 - Dec 19_19.pdf (9.3 MB)
Misery Underground - Land Use Inspection Report - September 10 2019 - Sep 13_19.pdf (16.6 MB)
Misery Underground - Land Use Inspection Report - June 25 2019 - Jul 5_19.pdf (2.39 MB)
Misery Underground - Land Use Inspection Report - April 30 2019 - May 9_19.pdf (3.48 MB)
Misery Underground - Land Use Inspection Report - March 19 2019 - Apr 1_19.pdf (1.96 MB)
Misery Underground - Land Use Inspection Report - January 22 2019 - Feb 8_19.pdf (2.84 MB)
Misery Underground - Land Use Inspection Report - October 18 2018 - Nov 21_18.pdf (3.18 MB)