Northwest Territories Power Corporation - W2018Q0003

This Permit entitles the Permittee to conduct the following land-use operation:a) use of a legacy borrow pit for the Snare Hydroelectric Facility near Snare Falls Plant; andb) use of equipment.
The Project is for Quarrying Operations and is located at the Snare Falls Plant.


Documents

Uploaded On or After
Uploaded On or Before
Displaying 1 - 2 of 2
2. Initial/Renewal Application
Consultations - Reviews - Work Plans
Document Received/Sent Uploaded
W2018Q0003 - NTPC - LUP Application - Borrow Pit - Review Summary and Attachments - July 12_18.pdf (1.68 MB)
W2018Q0003 - NTPC - DRAFT Land Use Permit - Borrow Pit - June 07_18.pdf (271.03 KB)