Arctic Canadian Diamond Company Ltd. - W2014I0001
Status:
Closed
Authorization:
Land Use Permit
Activity:
Powerlines
Start:
August 11, 2014
Expiry:
August 10, 2021
Staff:
Rhiana Bams
This Permit entitles Arctic Canadian Diamond Company Ltd. to conduct the following land-use activities in order to construct, install, and maintain power lines connecting the Ekati Mine main camp electricity to the Misery camp, along Misery haul road:a) the use of motorized drilling equipment in the construction and installation of power lines;b) use of equipment listed in the land use permit application dated May 22, 2014;c) construction of access pads extending from the north side of Misery Haul Road; andd) installation, operation, and maintenance of underground and overhead power lines.
The Project is to connect electricity from the Ekati Main Camp to Misery Camp along the Misery Haul Road near Lac de Gras, NT.
The Project is to connect electricity from the Ekati Main Camp to Misery Camp along the Misery Haul Road near Lac de Gras, NT.
Documents
Displaying 1 - 45 of 45
1. Permit - Licence - Other Issuances
2. Initial/Renewal Application
Document | Received/Sent | Uploaded |
---|---|---|
W2014I0001 - Ekati - LUP Application - May 22_14.pdf (2.14 MB) | ||
W2014I0001 - Ekati - LUP Application - NWT Lease Amendment - May 29_14.pdf (45.35 KB) | ||
W2014I0001 - Ekati - LUP Application Fee - Receipt - May 28_14.pdf (421.9 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
W2014I0001 - Ekati - LUP Power line Application - Review Summary and attachments_Jul 4_14.pdf (1.91 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
W2014I0001 - Ekati - Misery Powerline Supplemental to WLWB - Additional Information - Jul 23_14.pdf (892.76 KB) | ||
W2014I0001 - Ekati - LUP Power line Application - Review summary and attachments Jul 4_14.pdf (1.91 MB) | ||
W2014I0001 - Ekati - LUP Power line Application - Board Directive and Reasons for Decision - Jul 4_14.pdf (826.99 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
W2014I0001 - Ekati - Misery Power Line - Land Use Permit - Preliminary Screening - Aug 11_14.pdf (650.04 KB) |
4. Permit Extension Request
Document | Received/Sent | Uploaded |
---|---|---|
W2014I0001 - Ekati - Two-Year Extension Request - May 14_19.pdf (177.92 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
W2014I0001 - Ekati - Misery Power Line - Extension - Review Summary and Attachments - Jun 12_19.pdf (361.27 KB) |
5. Reports and Studies
Document | Received/Sent | Uploaded |
---|---|---|
W2014I0001 - Ekati - Misery Power Line - Map of Power Pole Locations - Aug 23_14.pdf (545.15 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
W2014I0001 - Ekati - Land Use Inspection Report - September 7 2016 - Dec 1_16.pdf (1.06 MB) | ||
W2014I0001 - Ekati - Land Use Inspection Report - September 28 2015 - Oct 20_15.pdf (1013.89 KB) | ||
W2014I0001 - Ekati - Land Use Inspection Report - May 27 2015 - Jun 5_15.pdf (1.01 MB) | ||
W2014I0001 - Ekati - Land Use Inspection Report - September 23 2014 - Oct 17_14.pdf (897.88 KB) |